Enviroearth accompanies the local government in its objective to reach 40% of renewable energy on the island by 2020. The installation of a solar farm is a first step toward this objective. It enables a cut in the use of fossil fuels and reduces the cost of energy for the local population. This project included several steps:
  • Conception and instalaltion of a 6.5kWp on-grid solar farm
  • Logistics management, Civil Works supervisions, construction and grid connection
  • Provision and installation of 5 solar water heaters to reduce the dependancy to natural gas
  • Commissionning and maintenance by an Enviroearth engineer
  • Tehnical and hands-on training of the end-users
  • Follow-up study taking into account all the parameters such as load profiles, condition of the local network and of the current energy generating system, environmental impact...