Enviroearth took charge of the whole realisation of the project, from the feasibility study until the final commissioning of a radioactive Xenon measuring station on Tristan Da Cunha.
This project included several tasks:
Definition of the technical specifications and Terms of Reference taking into account the very specific conditions of the island,
Design and provision of a water-resistant composite shelter made in France, connection to the local grid, installation of furniture and instrumentation material,
Logistics management in France and on-site
Management and supervision of Civil Works, installation of air-conditioning units, provision of Helium from South Africa
Permantent discussion with equipment suppliers, customer and local authorities to ensure the respect of local rules and regulations